Roof Project

Below is preliminary schedule for the Moonspinner Roof Project. This schedule is subject to change as there are a number of variables that can affect the timeline. All HVAC units will be removed in stacks and are expected to be down for no longer than 3 – 7 days. The 3 bedroom and penthouse units will not be disturbed. Preliminary Roofing/HVAC Schedule

ROOF 10/19/20 – 10/30/20 – Building “A”: original roof removed and temporary roof applied.

11/02/20 – 11/13/20 – Building “B”: original roof removed and temporary roof applied.

11/16/20 – 11/30/20 – Building “C”: original roof removed and temporary roof applied.

12/01/20 – 12/18/20 – Building “A” Install New Roof

12/21/20 – 01/08/21 – Building “B” Install New Roof

01/11/21 – 01/29/21 – Building “C” Install New Roof

02/01/21 – 02/12/21 – Gutters/Downspouts

02/01/21 – 02/12/21 – All Buildings: Lightning Protections

02/01/21 – 02/12/21 – Building “A” Deck Coating

02/22/21 – 03/05/21 – All Buildings: Punch out

03/08/21 – 03/10/21 – Demobilization

HVAC 11/02/20 – 11/20/20 – Building “A”: HVAC systems assessed, disconnected and reconnected. 11/23/20 – 12/11/20 – Building “B”: HVAC systems assessed, disconnected and reconnected. 12/14/20 – 01/06/21 – Building “C”: HVAC systems assessed, disconnected and reconnected.



Recent Posts

See All

August Meetings Information

The schedule for the upcoming Committee, Board, and Owners meetings is listed below. Please note that the Saturday, August 21st meeting will be held at the Sheraton Bay Point. Committee Meetings Thurs

Upcoming Election and Meetings

Moonspinner Owners, You will be receiving a ballot for the upcoming election. Please be sure to complete the ballot and return as instructed in the package. The following owners will be running for

Structural Concerns | June 30, 2021

Moonspinner Owners, Due to the recent collapse of the building in south Florida, owners may have questions about the structural integrity of buildings A, B & C at Moonspinner. The Moonspinner has a lo